NEW QUESTION # 18
Recognizing an employee as the "Star Performer of the Month" would be satisfying the _____ need of the Maslow's hierarchy of needs.
- A. esteem
- B. physiological
- C. self-actualization
- D. safety
Answer: A
NEW QUESTION # 19
The main output of the _____ process is the stakeholder register.
- A. Planning stakeholder management
- B. Controlling stakeholder engagement
- C. Managing stakeholder engagement
- D. Identifying stakeholders
Answer: D
NEW QUESTION # 20
The sigma means median.
- A. True
- B. False
Answer: B
NEW QUESTION # 21
Which of the following methods of communications is likely to be most effective for conveying sensitive or important information?
- A. E-mails
- B. Telephone conversations
- C. Short face-to-face meetings
- D. Reading reports from other team members
Answer: C
NEW QUESTION # 22
_____ are a complete set of organized project records that provide an accurate history of the project.
- A. Forecasts
- B. Project plans
- C. Project archives
- D. Project notes
Answer: C
NEW QUESTION # 23
_____ addresses how well a product or service performs the customer's intended use.
- A. Functionality
- B. Performance
- C. Reliability
- D. Maintainability
Answer: B
NEW QUESTION # 24
Projects that use Six Sigma principles for quality control normally follow a five-phase improvement process called _____.
- A. DMAIC
- B. use case modeling
- C. weighted scoring model
- D. configuration management
Answer: A
NEW QUESTION # 25
A(n) _____ is a document used to solicit proposals from prospective suppliers.
- A. WBS
- B. planning
- C. RFP
- D. RFQ
Answer: C
NEW QUESTION # 26
The _____ is a description of the work required for a procurement.
- A. WBS
- B. RFP
- C. RFQ
- D. SOW
Answer: D
NEW QUESTION # 27
The primary output of the planning cost management process is a change request.
- A. True
- B. False
Answer: B
NEW QUESTION # 28
The first step in deining the NPV is to _____.
- A. deine the discount rate
- B. deine the cash flow
- C. calculate the net present value
- D. deine the estimated costs and benefits for the life of the project and the products it produces
Answer: D
NEW QUESTION # 29
_____ are predefined actions that the project team will take if an identified risk event occurs.
- A. Contingency plans
- B. Management reserves
- C. Secondary risks
- D. Workarounds
Answer: A
NEW QUESTION # 30
The acquiring of the project team is a subprocess associated with the _____ process of project human resource management.
- A. controlling and monitoring
- B. planning
- C. initiating
- D. executing
Answer: D
NEW QUESTION # 31
_____ refers to the process of developing a working replica of the system or some aspect of the system.
- A. use case modeling
- B. variance
- C. prototyping
- D. decomposition
Answer: C
NEW QUESTION # 32
One of Juran's ten steps to quality improvement states that:
- A. an organization should entrust improvement to individual employees rather than appointing teams or facilitators
- B. an organization should avoid "keeping score" in order to achieve an overall atmosphere of quality improvement
- C. an organization should minimize top management involvement in the achievement of individual employee goals
- D. an organization should build awareness of the need and opportunity for improvement
Answer: D
NEW QUESTION # 33
_____ refers to a set of shared assumptions, values, and behaviors that characterize the functioning of an organization.
- A. chain of command
- B. organizational structure
- C. organizational culture
- D. line of control
Answer: C
NEW QUESTION # 34
......