NEW QUESTION # 46
Identify the impact of deleting a resource from the Resource Breakdown Structure?

  • A. Costs for past projects would be reduced because the cost associated with the resource is deleted.
  • B. Costs for past projects would not be affected as the actual have already been recorded In the database.
  • C. Budgets from past projects would be removed from the database.
  • D. Budgets for future projects would be removed from the database.
  • E. All actual and remaining work are removed from the database.

Answer: E


NEW QUESTION # 47
Identify two objects that cannot be changed once a Business Process has been imported into Unifier production instance.

  • A. Detail Forms
  • B. Workflows
  • C. Record statuses defined as terminal
  • D. Logs
  • E. Upper Forms

Answer: C,E


NEW QUESTION # 48
Identify two true statements regarding the rolling up of data within a Work Breakdown Structure (WBS).

  • A. Actual Data rolls up to a Portfolio level.
  • B. Actual Data rolls up to a Project level.
  • C. Actual Data rolls up to a Parent level.
  • D. Actual Data rolls up to Program level
  • E. Actual Data rolls up to a Resource level.

Answer: B,E


NEW QUESTION # 49
In addition to the four primary elements that comprise security, what additional feature in P6 Web will determine a user's access to data?

  • A. User Dashboards
  • B. Resources portlets
  • C. Portfolio Portlets
  • D. User Interface View

Answer: D


NEW QUESTION # 50
When assigning a user to a User Interface view, deselecting the Allow Editing check box restricts the user's ability to .

  • A. edit the User Interface View
  • B. edit his or her Resource Profile
  • C. edit project data in the view
  • D. edit his or her password

Answer: C


NEW QUESTION # 51
Identify two permission levels in Unifier

  • A. Partner
  • B. Shell
  • C. Administration
  • D. User
  • E. Company

Answer: C,E


NEW QUESTION # 52
All commands executed by toolbar icons can be accessed from three menus. Select the three menus.

  • A. Copy
  • B. View
  • C. Paste
  • D. Action
  • E. Remove
  • F. Edit
  • G. Modify

Answer: D,F,G


NEW QUESTION # 53
When viewing the Resource Usage Profile using the date interval of Week/Day1, resource a being displayed only on Sundays for every resource being analyzed. Why are all of the resource allocations being displayed on the same day of the week rather than across the days when they are scheduled to occur?

  • A. On the Resource Analysis tab, in the User Preferences dialog box, the "Interval for time-distributed resources calculations" field's set to "week."
  • B. All resources are assigned to the project's default calendar, and have been over allocated to other projects.
  • C. On the General tab. In the Admin Preferences dialog box, the first day of the week field is set to Sunday.
  • D. The resource calendar assigned to the resources was deleted by the System Administrator.

Answer: C


NEW QUESTION # 54
You are a Portfolio Manager with one project that is clearly underperforming. You would like to obtain more information about where the problems in the project reside. How would you do this in Primavera P6 EPPM Web interface without contacting the Project Manager?

  • A. Send an alert via workflow asking for more information from the Project Manager.
  • B. Create an Issue for follow-up by the Project Manager.
  • C. Send an email asking for more information from the Project Manager
  • D. Click the project name to view performance data by Work Breakdown Structure (WHS).

Answer: D


NEW QUESTION # 55
Generic Cost Code Shells .

  • A. support Cost Manager functionality
  • B. define the Shell hierarchy
  • C. define the Cost Breakdown Structure
  • D. support configurable modules

Answer: C


NEW QUESTION # 56
The Location tab in a Single Instance Shell is disabled because .

  • A. no permission has been assigned to locate the Shell
  • B. navigation tabs have not been configured
  • C. the Shell hierarchy is not defined
  • D. Single Instance Shells are always at the top of the hierarchy

Answer: A


NEW QUESTION # 57
What is the significance of the setting "Summarize project based on detailed activity resource assignments"?

  • A. Summarized project data will reflect Top Down plans
  • B. Summarized project data will reflect integrated Actuals.
  • C. Summarized project data will be monetized.
  • D. Summarized project data will reflect Bottom Up plans.

Answer: B


NEW QUESTION # 58
Identify the business case that would support the creation of OBS elements to align with WBS elements within individual project plans.

  • A. Large projects with multiple cross-functional learns that will be responsible for updating/maintaining one set of project data
  • B. Legal/regulatory requirements that prohibit users from seeing data across functional areas maintaining smaller sets of project data
  • C. Supporting data export/import process to minimize risk of degrading schedule quality
  • D. Mitigate the risk of significantly variant project management skill levels across an organization

Answer: A


NEW QUESTION # 59
Identify two benefits of customizing user-interface views.

  • A. User-based configuration
  • B. Administer users in the web interface
  • C. Limit user access to functionality
  • D. Target application functionality
  • E. Lock down security privileges

Answer: A,D


NEW QUESTION # 60
Your are coaching a Super User at a Customer site that is trying to respond to a specific organization''s request to only view data as they do currently in Excel.
Which Activity View functionality should be targeted for a Multi User View for this organization?

  • A. Calendar View
  • B. Activity Table
  • C. Activity Network
  • D. GANTT Chart

Answer: B


NEW QUESTION # 61
......