NEW QUESTION 70
During the Nexus Sprint Review of Sprint 2, some users have complained that the system is performing too slow.
What can the Nexus team do to manage user expectations? Select all that apply.
- A. Add the non-functional requirement to Definition of Done
- B. Work with stakeholders and agree on a tangible requirement
- C. It is too early to judge the performance of the increment
- D. Let the stakeholders use the wireframes and take the feedback
Answer: A,B
NEW QUESTION 71
Who is accountable for a releasable integrated Product being delivered at least once at the end of every Sprint?
- A. Scrum Master
- B. Product Owner
- C. Every Team member
- D. Nexus Integration Team
Answer: D
NEW QUESTION 72
What is the output of the Cross-Team Refinement event?
- A. Updated team structure
- B. Refined Sprint Backlog
- C. Refined Product Backlog
- D. Nexus Sprint Goal
Answer: C
NEW QUESTION 73
As part of the Nexus Sprint Retrospective, the team should address if there is technical debt in the product. True or False?
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION 74
Who is a mandatory member of Nexus Integration Team?
- A. Customer
- B. Product Owner
- C. Senior Development Team member
- D. Business Analyst
Answer: B
NEW QUESTION 75
Who is responsible for clearing the technical debt?
- A. Scrum Master
- B. Product Owner
- C. Stakeholders
- D. Nexus Integration Team
- E. Developers
Answer: E
NEW QUESTION 76
When is an increment DONE in Nexus?
- A. Only when integrated, usable and potentially releasable
- B. When every team member adheres to their Definition of Done
- C. Any usable increment without integration
Answer: A
NEW QUESTION 77
What should be done when one team is consistently performing better than the other teams?
- A. Changing team composition should be considered
- B. Release the low performing teams from the Nexus
- C. Assign low priority tasks to low performing teams
Answer: A
NEW QUESTION 78
You are part of Team A which is working on requirement #3. Team B is working on Requirement #6 which is very similar to yours. Your team discovered a limitation which would make it impossible to implement requirement #3.
When and who should you inform?
- A. Bring it up in Nexus Sprint Retrospective
- B. Wait for Team B to discover the issue on their own
- C. Bring it up in Nexus Daily Scrum
- D. Bring it up in Nexus Sprint Review
Answer: C
NEW QUESTION 79
What is the purpose of the Cross-Team Refinement event? Select two best answers.
- A. To determine a method to split the Product Backlog into multiple backlogs
- B. To refine the Product Backlog items granular enough for Scrum Teams to pull the work
- C. To select the Product Backlog items for the upcoming Sprint
- D. To identify and minimize dependencies between teams
Answer: B,D
NEW QUESTION 80
One of the key stakeholders sends an email to NIT Scrum Master. He is requesting the Nexus Sprint Review to be planned for 5 hours instead of 4, because the team is unable to demonstrate all the developed features.
What should the Nexus team do next?
- A. Agree, because stakeholders have a right to see every feature developed
- B. Discuss internally to evaluate if indeed 5 hours are necessary before responding to stakeholder
- C. Disagree, because Nexus framework does not allow the Nexus Sprint Review to be longer than 4 hours
Answer: B
NEW QUESTION 81
Which events are present and mandatory in Nexus but not in Scrum? Select all that apply. Daily Scrum Sprint Retrospective Sprint Review Cross-Team Refinement (Correct) Nexus Sprint Planning (Correct)
Answer:
Explanation:
Nexus has five additional Events: Cross-Team Refinement, Nexus Sprint Planning, Nexus Daily Scrum, Nexus Sprint Review, and Nexus Sprint Retrospective.
NEW QUESTION 82
Which is NOT the purpose of Nexus Integration Team? (Select two best answers)
- A. Be accountable that an integrated increment is produced
- B. Manage the Nexus
- C. Integrate the developers' work
- D. Raise transparency
Answer: B,C
NEW QUESTION 83
Nexus Integration team has defined a Definition of Done with 5 point criteria. One of the Sprint Team, want to use only 3 of them for their team's Definition of Done. Is this allowed?
- A. No
- B. Yes
Answer: A
NEW QUESTION 84
Select two correct statements about the Scrum Master in Nexus Integration Team.
- A. The NIT Scrum Master must coach the other NIT members to become self-organizing
- B. The same person can act as a Scrum Master for many Scrum Teams in a Nexus
- C. The NIT Scrum Master must be a Scrum Master for at least one of the Scrum Teams
- D. The Scrum Master of an individual team can act as a Scrum Master in NIT
Answer: B,D
NEW QUESTION 85
Membership of the Nexus Integration Team remains same through out the product development. True or False?
- A. FALSE
- B. TRUE
Answer: A
NEW QUESTION 86
Jim is a developer with several years of experience and he is part of Team A.
He is also part of Nexus Integration Team. During a Sprint, Teams B and C are struggling with integrating the work they performed.
At the same time, Team A requires Jim's involvement in completing a task. What should he do first?
- A. Jim should give priority to the task in Team A because NIT does not do real work
- B. Jim should give priority to the issue faced by Teams B and C
- C. Jim should give priority to the task in Team A because he belongs to that team
Answer: B
NEW QUESTION 87
Scaled Scrum is still Scrum. True or False?
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION 88
Requirement number 22 is being worked by Team C in a Nexus. Stakeholders are expecting this key feature to be demonstrated in the upcoming Nexus Sprint Review. Just 2 days prior to the review, the team identified a defect in one of the testing scenarios. It has been determined that Team C doesn't have the skillset to resolve the defect in such a short time. Select two BEST possible options the Nexus team can take to resolve the situation.
- A. Postpone the requirement to next Sprint
- B. Find the resources who have the skills and extend the Sprint to provide sufficient time to resolve the issue
- C. If a resource in other teams in Nexus has the skillset to resolve the issue, they should be brought in to NIT and the whole NIT can work on the issue
- D. NIT Scrum Master can look for specialists outside the Nexus who have the skills to resolve the issue
Answer: C,D